As part of a scheme to design and build a new Primary Settlement Tank (PST), OCU were contracted by Dwr Cymru Welsh Water (DCWW) as part of our Pressurised Pipework Framework Contract to carry out the design and installation of a new 10m Diameter Primary Settlement Tank (PST) with all associated civil, mechanical, electrical and instrumentation works and construction of site access roads.
The works comprised the construction of the PST with a half bridge mechanical scraper along with sludge pumping systems and full control and telemetry installation.
Aberbaiden WwTW receives its flow from 2 number incoming lines from the North, Southwest and West of the works and a foul line from the Southeast of the works. Both flows meet in a chamber before entering the works to receive treatment. Treated effluent is then discharged into to the River Usk.
The aim of the scheme was to increase Primary Treatment Capacity to allow for the works to cope with increasing incoming flow levels to the works. To facilitate this, the following scope of works was commissioned.
Scope of Works
OCU was responsible for all of the following activities on the project: